Assembly

Connect the two pipe pieces by putting the bolt through the axis holes. Place a washer on the outer ends and two washers between the pipes. Just hand tighten for now.

bolt placement


String the smaller diameter rope through the rope holes. Placing masking tape on the ends helps to keep the rope stiff while passing through the holes. I used pieces that were about 3ft in length. Tie off at the ends to prevent the rope from slipping out.

threading the hole threading both holes


Attach the pipe T-Joints to the bottom of the stands (side closest to the rope). Attach the two fifteen inch pieces to one of the T-Joints. Next, use either the shorter or longer cut base piece on the opposite T-Joint so that the ends of the base are almost flush. Cap all the pipe ends. Tie off knots on the rope ends to adjust the height of the stand.

flush base capped and ajusted